BIG BEND, Sonoma County — November 3, 2026. The highway junction at Big Bend is now a roundabout rather than the old stop-controlled intersection. Caltrans reports that its project partners celebrated completion of the Route 116/121 roundabout on October 24, 2025, following construction that began in 2024.
What was changed?
According to the state project description, the work widened portions of State Routes 116 and 121 and Bonneau Road, added pedestrian facilities and improved the intersection for bicyclists. Caltrans says the former stop-sign-controlled junction caused congestion, especially where turning traffic met through traffic. The new design aims to reduce severe crashes by lowering conflict points and speeds.
What did the work cost?
The project fact sheet lists approximately $27 million in cost and names funding contributions from the Sonoma County Transportation Authority, county sources and state highway maintenance funds. A listed project cost is not the same as an independently audited final expenditure, which would require the agency’s closeout figures.
How drivers should use it
Entering traffic yields to vehicles already circulating in the roundabout; drivers should slow, pay attention to lane markings and use the designated pedestrian crossings. The project should be distinguished from a separate proposed improvement at Route 121 and Eighth Street East, which remains under evaluation.
Primary source: Caltrans District 4 — Route 116/121 Roundabout. Readers should consult the agency for subsequent traffic conditions, implementation milestones or funding decisions.
Support Big Bend News
Choose how to support Big Bend News:
Credit / Debit Card via StripeChoose your contribution amount on the secure California58 Stripe checkout. One-time support for independent local journalism.
Continue with PayPal Continue with ZelleZelle payments go to Vitaly Ataev Troshin. Please verify the recipient in your bank before sending. Availability depends on your bank.
Optional reader support. When possible, add “Big Bend News” to the payment note. Contributions are not advertised as tax-deductible. Support does not influence editorial decisions.More from Big Bend News
- Highway 121 at Eighth Street East: Two Competing Safety Plans Remain Under Review →
- Sonoma County Backed New 2026 Funding Application for Schellville Trail →
- February 2026 Floods Closed Route 121 South of Sonoma: What Big Bend Drivers Should Know →
- Yellow Creek Bridge Near Big Bend Reopened After Early Completion of 2026 Rail Work →
COMMUNITY
Comments
Join the California58 conversation. You must be signed in to comment.
Create a free California58 account or sign in with an available social provider.